What does ‘the total cost of works’ mean?

Designer Binkie Moorhead and Saudi client Mashael Alebrahim fell out over the cost of refurbishing a flat in this building on Marylebone Road

Designer Binkie Moorhead and Saudi client Mashael Alebrahim fell out over the cost of refurbishing a flat in this building on Marylebone Road

Under a number of standard forms of building contract, the contractor’s entitlement to payment is often based on the cost of the works with the word ‘cost’ invariably simply meaning ‘the cost incurred by the contractor’. However, the Court of Appeal’s interpretation of the term ‘cost’ in a contract for interior design services in the recent case of Alebrahim v BM Design London Ltd [2022] EWCA Civ 183 is a reminder that the meaning of ‘cost’ is not fixed and ultimately depends upon the proper construction of each contract on a case-by-case basis.

Background

Saudi citizen Mashael Alebrahim owned a substantial flat in a late Victorian mansion block known as Harley House, on Marylebone Road in London. By written contract dated 7th April 2017, Alebrahim engaged BM Design London Ltd (the company of interior designer Binkie Moorhead) for an extensive refurbishment of the flat. BM’s work scope included procuring furniture, fittings and equipment (FF&E) for the flat.

Alebrahim made various claims against BD including but not limited to overpayment, delay and damages for loss of use of the flat. The pleadings were confused and confusing and some of the real issues between the parties did not come to light until the trial. Ultimately, the court at first instance dismissed all of Alebrahim’s claims.

However, one of the issues decided by the court at first instance was a question of contractual interpretation relating to the FF&E element of the works. Clause 10 of the contract stipulated that BM was entitled to payment of ‘20% of the total cost of the works’ plus the cost of the works procured for Alebrahim.

Alebrahim argued that ‘total cost’ meant the cost of the relevant items to BM and therefore if BM obtained trade discounts for FF&E items, that lower price benefit should be passed on to Alebrahim. However, BM argued that ‘total cost’ referred to the cost to Alebrahim; being the amount of the estimates provided by BM to Alebrahim and which Alebrahim approved.

The court at first instance preferred BM’s interpretation but found that if Alebrahim’s interpretation had prevailed, Alebrahim would have been entitled to recover approximately £100,000 from BM. On this basis, Alebrahim was given permission to appeal on this issue.

Outcome & conclusion

Related Information

The Court of Appeal dismissed Alebrahim’s appeal. The court found that the cost estimates prepared by BM and approved by Alebrahim informed the contractual payment process: Alebrahim was presented with breakdowns of the relevant FF&E items each week and, once the figures were agreed, they became the amounts that BM would invoice (with the addition of the 20% fee) and which Alebrahim would pay. Thus, as estimates were agreed by Alebrahim, they became part of the ‘total cost of the works’.

The contract only required that BM’s estimates were approved by Alebrahim; the way the estimates were calculated, and whether they were based on retail prices or included discounts was not relevant. Alebrahim was not obliged to approve the estimate and was free to purchase FF&E items from third parties. BM did not order any items until Alebrahim had paid it in line with the approved estimates. BM would obviously not wish to reveal to Alebrahim the details of its trade discounts and this common sense reality stood at odds with Alebrahim’s interpretation which would allow Alebrahim to challenge previously-agreed costs on the basis that a trade discount had not been passed on. This did not make sense and so BM’s interpretation was preferred by the court.

Under some standard forms of building contract, references to ‘cost’ may properly mean ‘costs incurred’ by the contractor. However, this case demonstrates that is not always the case and much will depend on the contract terms on a case-by-case basis.

The court remarked that the contract in the case “may not have been as immediately transparent as it should have been” in relation to the basis of the weekly estimates.  Alebrahim had wrongly assumed that the weekly estimates from BM would be based on trade prices without a mark-up.

The lesson for the parties is to ensure that the basis of both pricing and payments in their contracts is expressed clearly and well understood in order to avoid the prospect of unnecessary disputes.

About the authors: Kieran Shields is a trainee solicitor and Ben Couldrey is a solicitor in Irwin Mitchell LLP’s construction & engineering team.

About the case: Alebrahim v BM Design London Ltd [2022] EWCA Civ 183

Got a story? Email news@theconstructionindex.co.uk

Note: This article have been indexed to our site. We do not claim legitimacy, ownership or copyright of any of the content above. To see the article at original source Click Here

Related Posts
NZ economy shrinks, GDP falls 0.2% thumbnail

NZ economy shrinks, GDP falls 0.2%

Navigation for News Categories The economy unexpectedly contracted at the start of the year as consumers controlled their spending, exports dipped, and primary industries produced less. Gross domestic product (GDP) fell a seasonally adjusted 0.2 percent in the March quarter. Photo: 123rf Gross domestic product (GDP) fell a seasonally adjusted 0.2 percent in the three…
Read More
25_Changjiang Electronics Technology (600584) shares it_Oriental Fortune thumbnail

25_Changjiang Electronics Technology (600584) shares it_Oriental Fortune

发表于 2021-12-26 22:32:39 东方财富iPhone版 郑重声明:用户在财富号/股吧/博客社区发表的所有信息(包括但不限于文字、视频、音频、数据及图表)仅仅代表个人观点,与本网站立场无关,不对您构成任何投资建议,据此操作风险自担。 郑重声明:用户在社区发表的所有资料、言论等仅仅代表个人观点,与本网站立场无关,不对您构成任何投资建议。用户应基于自己的独立判断,自行决定证券投资并承担相应风险。《东方财富社区管理规定》
Read More
Recovery to be initiated in case of only unpaid self-assessed GST liability thumbnail

Recovery to be initiated in case of only unpaid self-assessed GST liability

Unpaid tax on self-declared supplies by a GST assesee will be considered as admitted liability, government sources said on Thursday. Accordingly, recovery can be initiated for that.For such recovery, however, any apprehension of unauthorised visits of GST officials to premises is ‘unfounded’. These explanations have come at a time, when some changes in CGST (Central…
Read More
Przetasowania i cenowy rajd na rynku węgla thumbnail

Przetasowania i cenowy rajd na rynku węgla

Drogi Użytkowniku! W związku z odwiedzaniem naszych serwisów internetowych możemy przetwarzać Twój adres IP, pliki cookies i podobne dane nt. aktywności lub urządzeń użytkownika. Jeżeli dane te pozwalają zidentyfikować Twoją tożsamość, wówczas będą traktowane dodatkowo jako dane osobowe zgodnie z Rozporządzeniem Parlamentu Europejskiego i Rady 2016/679 (RODO). Administratora tych danych, cele i podstawy przetwarzania oraz…
Read More
Index Of News
Total
0
Share